At Roberts Bank in Delta, British Columbia, beside the existing Deltaport and Westshore terminals and the lands of the Tsawwassen First Nation, the Vancouver Fraser Port Authority plans to build 168 hectares of new marine terminal landmass, causeway, and tug basin on federal port land. On October 30, 2026, through Privy Council Order P.C. 2026-1047, published in the Canada Gazette on November 14, 2026, the Governor in Council added that $5.9-billion expansion, Roberts Bank Terminal 2, to Schedule 1 of the Building Canada Act on the recommendation of Privy Council President Dominic LeBlanc. The listing triggers deemed fulfillment of substantive prerequisites for federal permits listed in Schedule 2 of the Act, even though Fisheries and Oceans Canada has not yet decided on the port authority's October 2024 Fisheries Act and Species at Risk Act application, and even as the Center for Whale Research counted 76 endangered Southern Resident Killer Whales remaining as of October 2026.
The order makes Roberts Bank Terminal 2 the second entry on Schedule 1 of the Building Canada Act, enacted on June 26, 2025, following the October 1 listing of the West Coast Oil Pipeline. Like that earlier order, P.C. 2026-1047 arrives with an Explanatory Note prepared with the Major Projects Office, a special operating agency inside the Privy Council Office. Unlike the pipeline, which entered Schedule 1 before route engineering or environmental assessments were finished, Roberts Bank Terminal 2 carries 13 years of federal review behind it, including a panel finding that the project is likely to cause significant adverse environmental effects.
What Listing Triggers Under Statute
As described in the Explanatory Note under subsection 5(1) of the Building Canada Act and the Act's permitting provisions, adding a project to Schedule 1 reorients federal regulatory decision-making in two steps. First, the listing triggers the immediate, deemed fulfillment of substantive prerequisites for federal permits and authorizations listed under Schedule 2 of the Act, including authorizations under the Fisheries Act and Species at Risk Act. Second, it allows diffuse departmental permitting processes to be consolidated into a single omnibus ministerial authorization, called a Conditions Document, issued by the responsible Minister after further assessment and Indigenous consultation.
For Roberts Bank Terminal 2, the Explanatory Note states that any federal regulatory authorizations granted prior to listing remain valid, while future authorizations are consolidated under the Act's framework. Listing does not exempt the port authority from enforceable conditions or required mitigation measures. Two federal approvals remained outstanding when Cabinet signed the order. On October 28, 2024, the Vancouver Fraser Port Authority applied to Fisheries and Oceans Canada for a Fisheries Act authorization that would also serve as a permit under the Species at Risk Act. Fisheries and Oceans Canada deemed that application complete in June 2025, and the Explanatory Note confirms that a decision on the authorization has not yet been made. The project also requires an authorization under the Canada Marine Act, along with any further approvals that arise during construction.
Rather than leaving those remaining permitting decisions solely to separate line departments, the Act shifts the federal process from whether a project should proceed to how it should proceed. Fisheries and Oceans Canada had already been consulting Indigenous communities on potential Fisheries Act conditions, and those discussions will inform post-listing consultation led with the Major Projects Office on the omnibus Conditions Document taking the place of key remaining federal permits and authorizations.
Thirteen Years of Review and 76 Remaining Whales
The environmental record cited in P.C. 2026-1047 dates back to September 13, 2013, when the Vancouver Fraser Port Authority submitted its project description to the former Canadian Environmental Assessment Agency. A Federal Review Panel submitted its environmental assessment report on March 27, 2020. That panel concluded that the three-berth terminal is likely to cause significant adverse environmental effects on Chinook salmon, the Southern Resident Killer Whale, Dungeness crab, bird species, wetlands and wetland functions, Indigenous land and resource use and cultural heritage, as well as cumulative effects.
On April 19, 2023, Cabinet issued Order in Council P.C. 2023-330 under subsection 52(4) of the Canadian Environmental Assessment Act, 2012, deciding that those significant adverse effects were justified in the circumstances. The next day, the Minister of the Environment issued a Decision Statement under section 54 setting legally binding conditions for construction and operation. On September 28, 2023, British Columbia's Minister of Environment and Climate Change Strategy and Minister of Transportation and Infrastructure jointly issued a provincial certificate carrying additional conditions.
The Explanatory Note treats the marine impact on Southern Resident Killer Whales as a central constraint. Listed as endangered under the Species at Risk Act since 2003, the whales were assessed as facing imminent threats to survival and recovery in 2018 and again in 2024. According to Center for Whale Research figures cited in the Explanatory Note, 76 Southern Resident Killer Whales remained as of October 2026, an increase of two from the 74 reported in 2025.
During construction and operation, the terminal is expected to increase underwater noise, destroy critical habitat, and reduce Chinook salmon prey availability. Under the 2023 Decision Statement, the port authority must stop construction work when marine mammals such as Southern Resident Killer Whales are near the site, and must delay container vessel departures and reduce underwater noise during berthing when whales are present. Since the 2023 Cabinet decision, the port authority has also revised its fish habitat offsetting plan and committed to 102 hectares of habitat offsetting. On climate targets, the Explanatory Note states that electric equipment and shore power connected to British Columbia's electrical grid are expected to give the terminal roughly 25 percent lower greenhouse gas emissions than comparable area terminals, though the 2020 Federal Review Panel found the project would still cause a small net increase relative to regional sources.
The Congestion Case and the $5.9-Billion Ledger
Cabinet's statutory rationale for listing the terminal rests on trade dependency and forecasted port bottlenecks. The Port of Vancouver moves $1 billion in goods every day, links Canada to 170 markets, connects to three Class 1 railways, and handles roughly half of all Canadian import and export containers alongside one-third of Canada's non-U.S. trade by value. Approximately 80 percent of Canada's non-U.S. trade travels by vessel, and the federal government has set a policy goal of doubling exports to non-U.S. markets by 2035.
Without expansion, the Explanatory Note states that the Port of Vancouver is forecast to reach maximum marine container-handling capacity in the 2030s. Cabinet estimates that insufficient capacity would begin costing Canadians an extra $800 million to $900 million per year in higher shipping costs as soon as 2031, while risking future reliance on U.S. ports for containerized imports. When November 2021 flooding cut rail capacity in British Columbia, disrupted goods movement cost an estimated $170 million or more per day.
Roberts Bank Terminal 2 is designed to add 2.4 million twenty-foot equivalent units of annual container capacity, a roughly 50 percent expansion of the port's container capacity sufficient to move about $100 billion in goods per year. The Explanatory Note estimates the project's capital cost at $5.9 billion, excluding financing costs, with completion projected for 2035. Combined with related rail and distribution investments, the project could lower container import costs by 25 percent, cut Vancouver-to-Toronto delivery times by 17 percent, and save Canadians roughly $1 billion a year in shipping-related costs. For the project itself, the government forecasts a $3 billion annual gross domestic product contribution, 17,000 supply-chain jobs during operations, and $631 million in annual federal, provincial, and municipal tax revenue.
To demonstrate delivery readiness, the Explanatory Note points to the port authority's track record at Deltaport (2010) and Centerm Terminal (2023), its selection of the TerraMarine consortium as preferred construction partner on July 13, 2026, and an April 21, 2026 Memorandum of Understanding with majority Canadian-owned operator Global Container Terminals. Financing arrangements and a final investment decision remain under negotiation among the Major Projects Office, the port authority, and federal partners.
Alongside project-specific conditions, the federal government cites $3.2 billion invested since 2016 in systems, research, and personnel to protect oceans and marine life, rather than killer whales alone. That broader ledger includes $258 million over five years in the Spring Economic Update 2026 to renew and enhance the Whales Initiative (encompassing a $163.8-million renewal and an additional $95 million plus $16.5 million ongoing specifically for killer whale protection), a $410-million five-year renewal of the Pacific Salmon Strategy, and a $1.2-billion Oceans Protection Plan renewal including over $100 million for whale protection. It sits alongside a Conservation Agreement with BC Ferries aiming to cut underwater radiated noise in killer whale critical habitat by 50 percent by 2036, as well as annual management measures for killer whales, including Transport Canada interim orders restricting vessel proximity and speed in Salish Sea foraging zones.
Ninety-Five Days of Consultation on Listing
Under subsection 5(7) of the Building Canada Act, the responsible minister had to consult federal colleagues, the British Columbia government, and Indigenous peoples whose section 35 rights could be adversely affected before recommending a Schedule 1 listing. Following a July 16, 2026 federal announcement and an August 29, 2026 Canada Gazette pre-listing notice, the Major Projects Office ran its listing consultation between July 17 and October 19, 2026, spanning 95 calendar days.
Officials identified 52 potentially impacted Indigenous communities based on the earlier environmental assessment list. The Major Projects Office held two virtual technical sessions, conducted more than 28 meetings with over 16 communities and organizations, and provided participant funding accessed by 30 eligible communities as of October 7. After communities raised scheduling conflicts with summer harvesting, cultural gatherings, and 2026 wildfire evacuations, the office extended its initial September 16 written submission deadline to October 1 and received 28 written submissions by October 16.
The Explanatory Note records a split between long-term project agreements and discomfort with the Building Canada Act itself. Through earlier consultation, the Vancouver Fraser Port Authority had already signed 27 mutual benefit agreements, reached Relationship Agreements with the Tsawwassen First Nation and Musqueam Indian Band, established an Environmental Co-Management Agreement with Tsawwassen, and created a $5.5-million Indigenous Legacy Benefit Fund. Most consulted communities had previously sent letters of consent or non-opposition to the project, and none signalled they would retract earlier environmental assessment consent if the terminal were listed.
Still, many Indigenous communities expressed discomfort with listing under the Act, warning of a perceived risk that the fast-track framework could weaken environmental protections, and few saw direct community benefits in the Schedule 1 designation itself. Most communities that opposed listing did so conditionally, requesting specific measures or an extended timeline given 2026 wildfire evacuations. None of the consulted Indigenous communities viewed the project as furthering Canada's climate change objectives, though some acknowledged it would carry a lower carbon footprint than comparable container terminals at the Port.
Cabinet concluded that delaying the listing decision was unlikely to produce new information given the project's 13-year regulatory history, and that remaining fish habitat and species-at-risk concerns could be addressed through an additional technical session on draft terms for the omnibus Conditions Document. Although P.C. 2023-330 had already cleared the federal environmental assessment hurdle in 2023, placing Roberts Bank Terminal 2 onto Schedule 1 while its Fisheries Act permit remained undecided fixes the federal permitting trajectory in law, shifting the remaining dispute onto what binding conditions will govern both construction and operation of the 168-hectare terminal.
Hansard Files is entirely free to read and funded by civic patronage. If you find value in independent reporting on Canada's public record, you can support our research.
Related Hansard Files Articles
Source Documents
Privy Council Office. (2026, October 30). Order Amending Schedule 1 to the Building Canada Act (P.C. 2026-1047) and Explanatory Note. Canada Gazette, Part I, Vol. 160, No. 46 (November 14, 2026), pp. 3175-3206. Ottawa: King's Printer for Canada.
Parliament of Canada. (2025, June 26). Building Canada Act (S.C. 2025, c. 2, s. 4). Ottawa: King's Printer for Canada.